ER-UPB single-room installation
5 | Metal discharge connection with shut-off damper |
18 | Main duct, steel folded spiral-seams duct |
19 | Connection duct, flexible aluminium duct AFR DN75/80 |
20 | Power cable |
37 | UPM 60/100 mounting support |
38 | Plaster protective cover |
39 | Cable grommet |
- Remove the plaster protective cover from the housing.
NOTICE The unit will be damaged and function impaired if the fixing screws used are incorrect/too long.Fixing screws may not penetrate into the housing.
- Use the screws provided (UPM 60/100 mounting support).
- Install the housing with the discharge direction (outgoing air wall connection) facing upwards, right or left.
- Mark the fixing holes for the mounting support on rear wall of the shaft/shaft wall, drill dowel holes and insert the steel dowels.
DANGER Danger of short-circuits and damage to the unit.If the cable grommet is not installed correctly, water may penetrate the housing. The degree of protection can no longer be guaranteed.
- Drive through cable grommet so that it can seal the cable sheathing all the way round (circular, no slots).
- Guide power cable from rear of housing through cable grommet into housing.
- Place the housing in the desired position and fasten it to the rear wall of the shaft/shaft wall with both mounting supports.
DANGER Fire may spread if connection duct is incorrectly installed.- Only use permitted duct material (Requirements in line with approval).
- Correctly attach connection duct to exhaust socket.
- Tightly connect the connection duct to the outgoing air wall connections, e.g. with cold-shrink tape.
- Make electrical connection.
- Insert the plaster protective cover in the housing.
- Plaster in housing flush with front edge, note tile thickness if necessary: Important information about plastering.