Additional RLS 45 K (slaves)

Activating slave control

  1. Install the RLS slave control unit in the flush-mounted box as described in the previous chapter.

Do not carry out commissioning until all ventilation units and system components have been completely installed. For commissioning, see chapter Commissioning

  1. Switch the mains fuse on. The ventilation units start up.
  2. In the service menu of the respective RLS 45 K control unit, select the setting parameter Power units, RLS on the RS 485 bus and activate the room air control unit (as slave 1, 2 or 3).

Alternatively, activation can also be carried out using the Commissioning software (Basic settings for specialist installer/number of power units).

  1. Carry out a function test after successful parameterisation. Test all accessory functions (signal strength, humidity function, etc.).